Put it into practice
- 1
Start with the status and the specific change since the last update. Apply your organisation's agreed RAG thresholds consistently.
- 2
Explain the impact on the next milestone, cost or benefit. Separate a confirmed issue from a risk that has not happened yet.
- 3
Close with the recovery action, accountable owner and target date. If leadership needs to decide, state the decision and the consequence of delay.
Evidence to build
Draft an amber status update with a cause, impact and recovery action. Check that a reader can identify what needs attention without asking you.